The Boankra inland port

The Boankra Integrated Logistics Terminal, on the Accra road east of Kumasi near Ejisu, is planned as an inland port where containers from Tema and Takoradi can be cleared and stored for Ashanti, northern Ghana and the landlocked Sahel countries. First proposed around the turn of the century, it lay idle for many years before a concession was signed and construction restarted in the early 2020s; the concessionaire once projected completion by March 2024 at a cost above US$300 million. Progress reports conflict. One 2026 report said the project had reached only six per cent of its target for April 2026 against a planned twenty per cent because of funding gaps, while a ports authority visit described the terminal area itself as nearly complete. In January 2026 the Turkish port operator Yilport held talks with the Ghana Shippers' Authority about developing and running it. In May 2026 the Asantehene warned against further delay and asked the government to speed up the work.

Note on the sources

Progress is reported as 6 per cent against a 20 per cent target (News Ghana, 2026), about 80 per cent of Phase One (Graphic, undated) and 98 per cent of the terminal area (MyJoyOnline, undated). These describe different scopes and possibly different dates.

Key facts

  • Boankra is planned as an inland dry port serving Ashanti, northern Ghana and Sahel states.
  • Yilport discussed the project with the Ghana Shippers' Authority in January 2026.
  • In May 2026 the Asantehene urged government to expedite the project.