Kejetia and Kumasi Central Market

Kejetia, in the heart of Kumasi, grew from a lorry station into the hub of what is often called the largest open market in West Africa, with well over ten thousand stores and stalls. Since 2015 the area has been under phased redevelopment. Phase one replaced the old Kejetia transport terminal with a multi-storey market complex of 8,420 shops built by the Brazilian contractor Contracta Engineering; work began in July 2015 and the building was handed to the Kumasi Metropolitan Assembly in December 2018. The Asantehene intervened publicly over the allocation of shops to traders and the market's reopening. Phase two, the rebuilding of the adjoining Central Market, began when President Akufo-Addo and the Asantehene cut the sod on 2 May 2019; it was budgeted at 248 million euros over forty-eight months but stalled, and in September 2026 work was reported as due to resume the following month.

Note on the sources

Phase one cost is reported as 198 million US dollars in one report and 259.4 million in another.

Key facts

  • Phase one: 8,420 shops, built by Contracta Engineering, handed over December 2018.
  • Phase two sod-cutting: 2 May 2019.
  • Phase two budget: 248 million euros over 48 months; later stalled.
View over Kejetia Market, Kumasi, 2010
View over Kejetia Market, Kumasi, 20102010-06-30 02:09 · Adam Jones from Kelowna, BC, Canada · CC BY-SA 2.0 · Credit and source
Traders at Kumasi Central Market
Traders at Kumasi Central Market2017-11-29 13:04:46 · Kyngky · CC BY-SA 4.0 · Credit and source