New hospitals: Sewua regional hospital and the Afari military hospital

For decades Ashanti had no purpose-built regional hospital, and pressure on Komfo Anokye led to two large projects on the edge of Kumasi. The 250-bed Ashanti Regional Hospital at Sewua in the Bosomtwe District, with a 50-bed infectious disease centre, was built by Euroget De-Invest under a contract dating from the late 2000s. President Akufo-Addo commissioned it on 4 January 2025, days before leaving office; the contractor publicly objected that the hospital was unfinished and that the ceremony breached the contract. President Mahama afterwards promised Asanteman that it would be completed without delay, but a June 2026 report described it as still not operating. A 500-bed military hospital at Afari, begun under the same contractor, was described as recently completed in January 2025, but no report confirming full opening was found. The Asantehene has pressed successive governments on both, and on the unfinished maternity block at Komfo Anokye.

Note on the sources

Government described Sewua as commissioned in January 2025; the contractor said it was incomplete. Afari's status is described inconsistently (completed versus yet to be completed).

Key facts

  • Sewua regional hospital (250 beds) was commissioned on 4 January 2025.
  • The contractor Euroget disputed the commissioning as premature.
  • A June 2026 report said the hospital was still not operational.